MCommunity System Development Process
1. Project Initiation
Deliverables
Project charge: The MCommunity Implementation Project Team will implement the architecture envisioned in Phase 1 and Phase 2 of the project, including identity management and access roles, data sharing and reconciliation, and directory services.
Staff members hired and teams formed. See About Us.
Overview schedule. See the Implementation Timeline.
2. Business Process Modeling and Requirements Gathering
Deliverables
3. Requirements Analysis
Deliverables
- Draft specifications
- Revised unit test plans
- Updated requirements documents if needed
4. System and Subsystem Design
Deliverables
- System design documents
- Design specifications
5. Building/Coding and Unit Testing
Deliverables
- System and subsystem coding
- Finished unit test plans
- Completed unit tests
- Module tests
- Updated design and requirements documents
6. Testing
Deliverables
- Integration testing (do the modules work together?)
- System testing (code will freeze after system tests are completed)
- Load testing
7. Deployment/Rollout/Release
Deliverables
- User training
- User documentation
- Announcements/communication
- Pre- and post-production tests
8. Stabilization
Deliverables
- Elevated monitoring levels
- Fix unanticipated problems
9. Production
Deliverables
- MCommunity fully implemented
- Maintenance windows set
- Operations documentation
- Upgrade planning
This page last verified February 27, 2009